Rectification Work for New Flats

In line with industry practice, all newly completed HDB flats are covered by a 1-year Defects Liability Period (DLP) effective from the date of key collection. During this time, we will follow up on items in the flat that require rectification.

It is important that you report the items within 1 month of key collection and before your renovation works begin. This will save the need to investigate whether the defects were inherent from HDB’s construction or caused by renovation works.

We usually take less than 2 weeks to complete the repair. In a situation where your renovation cannot wait, HDB can rectify the defects during the renovation (if it does not hinder your renovation) or after. Some minor defects can also be rectified after you have moved in (if living condition will not be affected).

 

Source by HDB